Last Updated on 1 day ago by Satrio
JCT Extension of Time: Common Mistakes to Avoid
When a contractor encounters a delay, it may affect the completion date and lead to a JCT extension of time request submission. Disputes over extensions of time often arise because the supporting evidence is insufficient, the contractual basis is unclear or the notice does not explain the delay sufficiently. From the contractor’s perspective, disagreement may arise where the assessor rejects the claimed entitlement or grants a shorter extension than the contractor considers justified.
An Extension of Time (EOT) may be granted or assessed to adjust the contractual completion date where a qualifying cause arises and the relevant contractual requirements are satisfied.
Recognising the common mistakes will enable contractors, contract administrators, and employers’ agents to handle delay procedures in a better way. This article discusses the common mistakes encountered in the making of JCT Extension of Time claims.
Why do JCT Extension of Time Claims Become a Dispute?
JCT claims for extension of time are contested because a visible delay is not the same as a proven entitlement to more time. The contractual assessment is whether a qualifying event has delayed, or is likely to delay, completion beyond the relevant completion date.
Often there are three separate questions in one: did a delay event occur, does the contract recognise it, and did it impact completion? This is why there are disagreements. The Society of Construction Law (SCL) Delay and Disruption Protocol views disruption as a loss of productivity separate from delay. One of the fundamental values of the SCL Delay and Disruption Protocol is proper records. Most disputes are shaped by two points:
- Delay to progress vs delay to completion: An interruption to an individual activity will not cause a delay to completion unless it affects the work that controls the completion date.
- Contractual entitlement and evidence of entitlement: Separate evaluation of the event, its contractual characterisation and its actual effect on completion. Here we define Relevant Events and elaborate on them in more detail below.
Common Mistakes on JCT Extension of Time
There are various procedural and evidential pitfalls that can undermine JCT extension of time claims. These include late notifications, misclassification of Relevant Events and inadequate supporting records.
The consequences are subject to the relevant terms of the contract, its amendments, and the circumstances. The table below sets out some common mistakes and practical steps that can help prevent disputes during assessment:
| Common mistake | Potential consequence | Preventive action |
|---|---|---|
| Failure to give timely notice | Circumstances of delay may not be properly communicated or assessed. | Inform the concerned party as per the contract. |
| Incorrectly identifying or classifying the Relevant Event | The entitlement claimed may not correspond to the applicable contractual basis. | Review the Relevant Events provisions and identify the event relied upon accurately. |
| Providing incomplete particulars | The assessor may not have sufficient information to assess the claimed delay. | Explain the event, its effects, and the estimated impact on completion. |
| Running an outdated programme | Delay analysis may not reflect the actual project progress. | Keep the programme records up to date. |
| Assuming all site delays impact completion | The required extension may not be supported. | Check the effect on the completion date. |
| Mixing time and financial claims | They may misunderstand different contractual entitlements. | Evaluate loss and expense and EOT individually. |
Spotted a mistake you could be making in your own EOT claims? Our course advisors can help you with the right JCT training. Speak to the team through the chat icon below.
Misunderstanding Relevant Events Under JCT Contracts
A Relevant Event is an event recognised under the JCT contract that may give rise to an extension of time where the applicable contractual requirements are met. The types of events listed in JCT contracts that may be used as the basis of a claim have to be identified, and the claim should relate to one of those. Incorrectly identifying the event or using an event not included in the contract weakens even a valid claim.
Grounds vary by contract format, version, and any variations, so refer to the terms actually signed rather than a contract overview. There are three main issues, such as:
Determine Which Events are Relevant
Relevant Events may include certain employer instructions, certain employer-related delays, and other events expressly identified in the contract. The contractor has to determine which provision applies and the effect of the event on the works. The particular terms depend on which JCT you use.
Assuming all delays are eligible for an extension
Not all delays are Relevant Events. Relevant provisions may not support extensions of time if delays result only from the contractor’s own performance, insufficient resources or poor planning. Even if an event is qualifying, the effect of it on the date of completion of the contract has to be proved.
Ignoring Changes in JCT 2024
The JCT Design and Build Contract 2024 introduced or expanded provisions dealing with epidemics, changes in law or official guidance and certain discoveries of asbestos, contamination or unexploded ordnance. Whether these provisions are applicable depends on the wording and the agreed arrangements of the contract. These provisions should not be interpreted as automatically entitling the contractor to an extension of time.
Incomplete Delay Notices and Supporting Particulars
A JCT extension of time notice is a notification of events that could impact the progress and completion of construction. If the notice or supporting particular are insufficient, the relevant party may be unable to investigate the event properly or assess its effect on progress and the contractual Completion Date.
The contractor shall comply with the notification requirements of the specific form and edition. The timing, recipient, and information required must be double-checked against the signed contract and not assumed based on general industry practice.
Under the JCT Design and Build 2024 contract, clause 2.24 refers to the contractor’s delay notice, while clause 2.24.4 gives the employer 14 days for making an information request. Following that, the employer now has eight weeks instead of the previous twelve under clause 2.25.2. However, other 2024 versions of JCT may vary; thus, the particular JCT form and amendments should be consulted.
- Delay in giving first notice: Clause 2.24 demands that notice be given as soon as the delay is reasonably apparent. If the contractor waits until they know the full effect, they have a poorer record of what was known and when it happened.
- Failing to provide essential delay particulars: Particulars should describe the event, its cause, its effects and the estimated delay to completion and be updated if circumstances change.
- JCT 2024 Misreading Assessment Periods: The 14 days is the employer’s time to request more information, not the contractor’s deadline to submit a claim. The decision period of eight weeks starts from the later of the particulars and any information requested. The JCT itself notes that the wording does not expressly provide for what happens if the 14 days is not met.
Want to understand JCT 2024 notice and assessment periods in practice? Ask our course advisors about the Professional Diploma in JCT Contracts using the chat icon below.
What Evidence is Needed to Prove Delay to Completion?
Evidence needed to prove delay to completion includes a current programme, actual progress records, and contemporaneous documents that show how the event affected the work delivery process. It is hard to justify an extension of time when the evidence shows activities have been disrupted, but completion has not been impacted. Assessors depend on programmes and records, so a gap there undermines a real delay.
In addition, construction delay analysis needs information on planned actions and real progress, as well as any changes to these that occurred. It is important to choose an appropriate method of analysis based on the records available. The table below outlines the project records and their purpose for an EOT assessment:
| Record | Purpose in an EOT assessment |
|---|---|
| Baseline programme of construction | Create scheduled activity sequences and completion times. |
| Programme revisions | Present any changes in progress and completion dates. |
| Site records | Records site activities, interruptions, and resource usage. |
| Instructions | Portray the instructions for the work to be carried out. |
| Correspondence and notices | Captures communication about the delay conditions. |
| Progress meeting records | Support the chronology of events and decisions. |
Need stronger delay analysis and claims skills? Ask our course advisors which course suits your role using the chat icon below.
Confusing Extensions of Time With Loss and Expense
The extension of time and loss and expense claim are two distinct contractual consequences. An EOT is about the date of completion; loss and expense provisions are about the possibility of financial recovery.
The contractor may have a basis for an extension of time, without necessarily being entitled to payment. Each entitlement should be tested against the ‘relevant’ contractual requirements and supporting evidence.
- Extension of Time and adjustment to the Completion Date: Where the contractual criteria are satisfied, an EOT may result in an adjustment to the Completion Date in accordance with the contract.
- Loss and expense under separate clauses: JCT employs Relevant Events for extensions of time and Relevant Matters for loss and expense; hence financial claims are made separately.
- Difference between time and cost evidence: Evidence of delay and programme will be different from evidence of cost.
What Should You Check Before Submitting a JCT Extension of Time Claim?
Before submission, ensure you have checked the contract form, Relevant Event, notice, evidence of effect on completion and whether any claim for loss and expense is maintained separately. Additionally, the final review must determine whether the mentioned period can be substantiated by the information available and whether the individual financial assertions should be looked into. The key steps are:
- Contractual provisions: Verify the form, version and modifications of the JCT.
- Reasons for Relevant Event: Determine the basis for extra time.
- Proper notice: Review the addressee, timing and necessary details.
- Proof of delay: Establish the impact of the event on completion.
- Programme alignment: Align the facts with the period.
- Entitlement to money: Assess claims for loss and expense independently.
Consider a contractor operating under JCT Design and Build 2024 where the critical installation is delayed due to late employer design information. A good review sets the contractual event, checks the notice, tests the programme evidence, assesses the probable completion impact and completes the particulars, without assuming entitlement. However, whether the contractor or the employer takes the hit in terms of time and cost will depend on the allocation of risk in the contract. So, the next step is to look at the allocation of risk in your JCT contract and what to check.
Frequently Asked Questions
| Are all construction delays entitled to an extension of time under JCT? No. The delay has to be related to a qualifying event under the contract, and it has to be shown that the event has an impact on the completion date. A delay caused by the contractor’s own work or a delay that does not impact the controlling work is not itself a basis for an extension. |
| Does a late JCT extension of time notice kill a claim? It is contingent upon the wording of the contract, any amendments and the circumstances. Late notice can certainly damage a claim and restrict the information available for review, but it is not an automatic denial. Before assuming the consequences, check how your contract treats notices. |
| How long does a JCT extension of time claim take? JCT Design and Build 2024 requires the employer to consider a claim within eight weeks of receipt of the particulars or further information if requested. So the start date is dependent on when the particulars come in, and on whether additional information is properly requested. |
| Can contractors claim extra costs with a time extension? No, not by default. An extension of time changes the date for completion; loss and expense are covered by separate clauses and have their own requirements and evidence. A successful EOT may support a cost claim, but entitlement needs to be established separately. |