The Joint Contracts Tribunal (JCT) publishes standard forms of construction contracts which are used on many types of UK building projects. A project team faced with a choice between them finds that the forms are not interchangeable.

The correct form will depend on the procurement method, the complexity of the work, the party responsible for design, the way the work is priced and the amount of contractual administration required by the parties.

This guide compares the principal types of JCT contracts and explains the practical points that professionals should be aware of before choosing one. It refers to the JCT 2024 edition, the current edition, although older contracts may still be found.

What are the Different Types of JCT Contracts?

JCT has several contract families, each of which has its own different project type and procurement setting. The popular ones are the Standard Building Contract, Intermediate Building Contract, Minor Works Building Contract, Design and Build Contract, Major Project Construction Contract, and Target Cost Contract.

JCT also produces specialist forms. Within a contract family there can be a main contract, sub-contracts, guides, variants, etc. These should therefore not all be counted as separate main contract types. The JCT contract families include:

  • Standard Building Contract (SBC): Administration of traditionally procured projects.
  • Intermediate Building Contract (IC): The middle range of contract administration procedures.
  • Minor Works Building Contract (MW): Simplified procedures for minor works.
  • Design and Build Contract (DB): Design and build responsibility of the contractor.
  • Major Project Construction Contract (MP): Simplified procedures for major projects where the participants are experienced.
  • Target Cost Contract (TCC): Target cost contract and financial sharing.
  • Management Building Contract (MC): Management contracts including works contractors.
  • Construction Management Contract (CM): Direct contractual dealings with trade contractors.
  • Measured Term Contract (MTC): Work carried out at regular intervals in the agreed period.
  • Prime Cost Building Contract (PCC): Prime cost-based construction.

JCT Contract Types: Core Functions and Uses

These various JCT forms vary in respect of the procurement approach, requirements of the project and nature of the contract. The following is a comparison of the various forms in terms of the major distinguishing factor and application of each form.

Contract type Main feature distinction Practical application
Standard building Specific procedures for projects procured conventionally More complex or larger building works
Intermediate building Procedural detail (moderate) Projects requiring a middle administration approach
Minor works Relatively simple provisions Small, Simple Building Projects
Design and build Contractor is responsible for design and construction Design and build procurement projects
Major project construction contract Design and build contract with limited prescribed procedures, reflecting the parties’ own detailed systems and greater contractor risk responsibility. Large-scale projects involving experienced employers, contractors and advisers, where the contractor assumes significant design and risk responsibilities.
Target cost Joint financial results and target costing Projects applying for cost incentives for collaboration
Management building Management contractor works contractors use Management of Procurement
Construction management Trade contractors are contracted directly with the employer. Procurement in construction management
Measured term Arrangement of term — Recurrent works Maintenance and minor works schedules
Prime cost Cost reimbursable plus fee Projects where a traditional fixed price may not be suitable

The contract form should be in line with the actual procurement and project arrangements. If the form does not match the way the project is procured, designed and priced, it will create gaps between the paperwork and the way work is delivered. There are also three types of Standard Building Contract:

  1. With Quantities (SBC/Q): The contract documents include bills of quantities.
  2. No Quantities (SBC/XQ): Pricing is established on other documents such as specifications or drawings.
  3. Approximate Quantities (SBC/AQ): Approximate quantities are included in the bills and are measured as the work proceeds.

How can Procurement Methods Influence JCT Contract Selection?

Selecting a JCT Contract will depend on which procurement method is chosen, since the procurement strategy is made before the contract form. In the JCT 2024 edition, it is stated that the procurement approach and contractual agreement should be the first thing to be settled, and then proceed with choosing the contract form to fit the procurement and contractual arrangement.

The choice is framed by three broad approaches. JCT also supports integrated and partnering arrangements which are not dealt with in this guide:

  • Traditional procurement: Involves the employer’s team designing the project and the contractor building it, with a contract administrator overseeing the process. This approach is usually followed for the Standard Building, Intermediate Building and Minor Works contracts.
  • Design and Build procurement: The contractor undertakes both design and construction to the employer’s requirements. This leads to the Design and Build Contract or to allied contractor-design forms.
  • Management procurement: The difference is in the contractual relationships. In management contracting, the works contractors are appointed by the management contractor, whereas in construction management, the trade contractors are appointed by the employer directly.

Design Responsibilities Across Different JCT Contracts

Design responsibility is among the most explicit distinctions in JCT forms, but this cannot be determined from the name of the contract. This is dependent on the contract form and the manner in which it is prepared.

There are two points to consider. A Standard Building Contract does not necessarily transfer all design responsibility to the employer, nor does design and build remove all design responsibilities from the employer.

Employer-Led Design in Conventional Contracts

In the case of the traditional forms, the employer normally provides the design information in the contract documents and the contractor builds to it. The Standard Building Contract provides for a contractor’s designed portion where the documents permit.

Contractor Design for Design and Build Contract

The contractor is responsible for both design and construction and works from the employer’s requirements and its own contractor’s proposals. The documents are important because they determine what is to be built. The employer is still responsible for what its requirements say.

Parts of Traditional Works Designed by Contractor

JCT also provides variants for limited design by the contractor, such as the Intermediate Building Contract with Contractor’s Design (ICD) and the Minor Works Building Contract with Contractor’s Design (MWD).

Unsure how design responsibilities differ across JCT contract forms? Use the live chat icon below to speak with the course advisors about relevant JCT training.

What is the difference between the pricing arrangements for JCT Contracts?

Construction contracts under JCT provide for various ways in which construction costs can be handled. This will depend on the amount of information that is known and the certainty of quantity. There are construction contracts that run mainly on lump sum pricing. Other contracts allow for measuring, cost-reimbursing, and target costing arrangements.

  • Lump sum pricing: Used in the relevant Standard Building, Intermediate Building, Minor Works and Design and Build contracts. The contractor agrees a sum for defined work. Adjusted only as the contract provides.
  • Costs of measurement and reimbursement: The measurement arrangements value work in measured quantities measured at agreed rates. Cost reimbursement pays the contractor’s actual costs plus a fee. This is good for work that is hard to price up front, as with prime cost contracts.
  • Target cost and pain/gain share: The Design and Build Contract 2024 is the basis for the Target Cost Contract 2024, which was issued on 25 June 2025 used an agreed Target Cost together with payment of Allowable Cost, the Contract Fee and, where applicable, a Difference Share. It is cost-reimbursable and has a target cost incentive so that if a contractor comes in under the target, he shares in the gain. The contract shares the overspend when costs exceed the target.

Interested in developing your knowledge of JCT pricing and commercial responsibilities? Speak to our team through the live chat icon below to explore opportunities in joining the programme.

How to Choose JCT Contracts for Different Project Requirements

Choosing a JCT form involves considering the complexity of the project, the state of design, costing needs, responsibility allocation, specialist and administrative needs.

The table below provides indicative examples and not definitive legal advice. Always refer to the form against the project documents and seek professional advice when necessary.

Project requirement Potential JCT forms to choose Main reason
Simple, uncomplicated projects Minor works Easier contract processes.
Moderately complicated traditional project Intermediate building Suitable level of procedural detail.
Highly complicated employer project Standard building Greater contract detail.
Design and Construction by Contractor Design and build Combines design and construction processes.
Project with agreed cost-sharing incentive Target cost Financial cooperation using target cost agreements.
Recurring maintenance programme Measured term Term contracts for repeat work.

Want to strengthen your understanding of JCT contract selection and procurement arrangements? Ask our course advisors about the JCT Contract training programme by using the live chat icon below.

What Should Professionals Understand on JCT 2024 Contract Updates?

In the JCT 2024 edition, Collaborative Working and Sustainable Development and Environmental Considerations were moved from the previous Supplemental Provisions into the main contract provisions. Therefore, they are no longer presented simply as optional supplemental clauses in the JCT 2024 forms.

It is important to understand the difference between JCT 2016 and JCT 2024, as you may come across the older JCT 2016 contracts and you will have to work from the edition that is actually incorporated in the contract. Four updates are most important in day-to-day contract use:

  • Target Cost Contract Family: A new family, which finished publishing the 2024 suite in June 2025.
  • Notices and communications: Notices may be sent by email if so specified in the contract particulars, on an all-or-nothing basis, with some notices excepted.
  • Extension of Time: The time for the granting of an interim extension has been reduced from 12 to eight weeks, and new events have been added, such as epidemics and changes in law.

Nevertheless, understanding what has changed is only the start. Often problems emerge once a contract is live, such as late or invalid notices, disputed extensions of time or a form that no longer reflects how the project is being delivered. Our guide to solving common JCT contract issues explains how to identify the cause and take practical corrective action.

Frequently Asked Questions

Which JCT contract is best for small projects?

The Minor Works Building Contract is intended for small, relatively simple work where the procedures are also simple. The complexity of the project is more important than the value alone. A low-value job with significant design or risk issues may require a fuller form. Check the scope and documentation first.

What is the difference between JCT Standard Building and JCT Design and Build?

The Standard Building Contract usually requires the employer to provide the design and the contractor to build to it. In a design and build contract type, the contractor is responsible for design and construction according to the employer’s requirements. Usually, the procurement route and design responsibility decide which fits.

Can JCT contracts be utilised for refurbishment works?

Yes, depending on the nature of the project as regards its complexity and the particular type chosen. For instance, a simple refurbishment may fall under Minor Works, whereas a complex refurbishment may require Intermediate Building or Standard Building. The final construction documents will decide on the allocation of risks.

Is JCT 2016 still effective after JCT 2024?

Yes. This is because the applicable edition is the one that was agreed by the parties in their agreement. Therefore, professionals must rely on the documents of the agreement rather than the new version, which comes into effect automatically.