FIDIC Claims Rejected: Why and How to Strengthen The Claim?
Can a claim under a FIDIC contract still be rejected? Yes. An event genuinely causes delay or additional cost does not establish a successful contractual claim alone. Although FIDIC is an established standards organisation, that does not mean that claims under is inevitable. FIDIC claims are typically rejected because the claim submitter could not prove contractual entitlement, comply with the contract’s requirements, or provide sufficient relevant evidence of the actual time or cost impact throughout the project.
A delay or additional cost occurring on a project does not truly translate into a valid claim. It should be followed by the correct entitlement related to the parties involved in a project. Related to a FIDIC contract, a successful claim depends on three key areas: compliance with the contract’s requirements, solid supporting evidence, and a clear connection between the cause of the event and the requested relief.
This article gives reasons for the rejection of FIDIC claims, features of a FIDIC claim that can strengthen it from the perspective of the contract, the kind of evidence required to back up such a claim, and pre-submission considerations. This way, the reader will be able to identify potential weaknesses beforehand.
What Makes a FIDIC Claim Valid?
A FIDIC claim is valid when it establishes contractual entitlement, complies with the contract’s procedures and requirements, and clearly demonstrates the impact of the claimed event. Moreover, these three elements sync with each other; missing any of these elements can make a claim easy to challenge or reject, regardless of whether the event genuinely occurred or not.
As the three elements sync with each other, the connection starts from how entitlement establishes whether a claim can exist, then compliance and procedure determine the recoverability, and demonstrated impact allows the claim to be assessed, valued, and awarded. Look at the explanation of each element below:
Contractual Entitlement
The claimant must prove where the entitlement is derived from the contract, if the situation fits in the clause, and any contractual remedy that might result. These include certain Variations, delays leading to an entitlement through another clause in the contract, exceptional weather conditions, unforeseen shortages due to epidemic or government interference, and any other delay.
Compliance With Contract Procedures
It does not matter that even an otherwise technically proper event will be difficult to retrieve if notices and time limits are not adhered to. According to FIDIC’s Sub-Clause 20.1 (1999) or 20.2 (2017), a Notice of Claim is required to be submitted within 28 days after the occurrence of an event, which has been held by the courts to be a condition precedent.
Demonstrating Impact
The claim must make all these connections, and not merely state what occurred. That is, the entire process from the event to the desired relief must be presented:
Contractual Basis → Cause → Effect → Entitlement → Quantum / Relief Claimed
This structure reflects FIDIC’s own guidance on claim preparation. FIDIC’s Construction Claims & Responses – effective writing & presentation explains that a claim can be organised into sections covering the contract, cause, effect, entitlement and quantum.
Common Reasons FIDIC Claims Are Rejected
In most cases where claims have been rejected under FIDIC conditions, it is not because the event did not occur. They fail because of how the claim was managed procedurally, the submitted evidence, and how clear the argument was regarding the claim. The issues tend to appear across different projects or disputes.
It is important to understand the pattern, since it can be avoided by implementing the right procedures and habits from the start of the project, rather than fixing it when a claim is disputed. The table below shows the common reasons why FIDIC claims are rejected, along with their cause and effects within a project.
| Reason | Why It Happens | Effect |
|---|---|---|
| Missing or late notices | Late notification beyond 28 days, incomplete notification, or inadequate specification of the event. | Entitlement may be completely lost due to failure to provide notice, as it is regarded as a condition precedent. |
| Insufficient supporting evidence | Insufficient record-keeping during the course of the project, especially programme and cost. | The claim is hard to prove even when the incident has taken place. |
| Failure to establish cause and effect | The described claim does not connect to the actual impact. | The claim appears more like an assertion and not a proper claim. |
| Weak extension of time claims | There is no programme, delay analysis, or critical path impact analysis, particularly regarding concurrent delay. | Entitlement to extra time is disputed or denied. |
| Poor cost substantiation | Unsubstantiated costs, lack of records, or unclear calculations for an additional payment claim. | Financial compensation is denied due to lack of evidence. |
| Incorrect management of variations | Inappropriate instructions for changes, unclear valuation or records. | Arguments regarding entitlement and value that should have been avoided with clear instructions. |
| Misunderstanding dispute procedures | Failure to adhere to the procedure in the contract, for example, Engineer’s determination, DAAB and Arbitration. | Arguments escalate faster than they should have. |
Sources: CMS “New FIDIC Second Editions”; Fenwick Elliott; FIDIC’s “Papworth Claims” guidance; Gowling WLG “FIDIC Claims for Time”; CMS “Concurrent delay update”; FIDIC Capacity Building Programme
Worried your FIDIC claims could fail on notice or evidence? Chat to our course advisors about Professional Practice in FIDIC Contracts through the chat icon below.
What Kind of Evidence Supports a Strong FIDIC Claim?
A stronger FIDIC claim can be supported by evidence like contract documents, project records, programme evidence, and cost records. Furthermore, FIDIC claims particularly depend on evidence across several distinct categories rather than a single document. Missing one category can result in a genuine claim being open to contest by the opposing barrister.
Gathering the evidence is not something that can be done after a dispute has started. This thing depends on project records being kept properly, far before the claim is submitted. Take a look at the table below to know what kind of evidence can support FIDIC claims and what each includes:
| Evidence Type | What It Includes |
|---|---|
| Contract Documents | Conditions of the contract, specifications, and instructions issued pursuant to the contract |
| Project Records | Daily reports, meeting minutes, and correspondence between the parties |
| Programme Evidence | Baseline programme, updates thereto, and delay analysis demonstrating effect on critical path |
| Cost Records | Invoices, labour records, and resources supporting the value of claim |
How to Strengthen a FIDIC Claim Before Submission?
Building a better case does not mean that you have to write it persuasively. It means ensuring that all the fundamental elements discussed above are present before you make your claim. This process eliminates the possibility of forgetting any element, which could eventually destroy the entire case you are trying to build.
The following steps are presented in a logical sequence of how a claim should be built, from verifying its contractual basis to putting together your submission.
- Verify contract entitlement: Look for the clause and verify the contractual basis of the claim.
- Collect evidence: Gather all records, correspondence, and programme data under the categories listed above.
- Prove impact: Show the time impact, the cost impact, and the causal relationship between both.
- Build a solid submission: Prepare your submission in the form of a story supported by documents and calculations.
Want to build FIDIC claims with a clear contractual basis and evidence? Ask our course advisors about claims preparation training using the chat icon below.
Key Differences Between A Strong and Weak FIDIC Claim
Two claims emanating from an almost similar project event may have different results based on the strength of proof with respect to the contractual basis, procedure, and effect.
While a relatively weak claim only narrates the events that took place, a strong claim correlates the event with the contractual basis, adheres to the procedure, and proves the need for the time or money demanded. The following table demonstrates such variations.
| Category | Weak Claim | Strong Claim |
|---|---|---|
| Contractual Basis | References a delay or expense but does not specify the clause. | References the particular FIDIC sub-clause on which the claim is based (for instance, Sub-Clause 8.5 for an extension of time) and confirms that it falls within its terms. |
| Notice Compliance | Late or poorly labelled Notice of Claim. | Notice of Claim is issued within 28 days pursuant to Sub-Clause 20.1 (1999) or 20.2 (2017) of the contract, and properly identified in writing. |
| Delay Analysis | No programme analysis submitted in conjunction with the claim. | Delay analysis demonstrating how the particular event has affected the critical path, including any concurrent delay issue. |
| Submission Timing | Detailed claim submitted either late or not present. | The fully developed claim made within the appropriate time frame (42 days for 1999 and 84 days for 2017). Specific itemised cost documents relating to the claim event, such as invoices, labour costs, and other resource costs. |
| Cost Evidence | Costs submitted in a lump sum without documentation. | Detailed costing documentation such as invoices, labour costs, and resource information relating to the actual incident in question. |
Want to move from weak claims to strong and well-evidenced ones? Discuss with our course advisors to know which course fits your role by clicking the chat icon below.
How Professional FIDIC Knowledge Helps Improve Claim Outcomes
Knowing the principles is one thing, but putting them into practice under an active contract, especially under time pressure, is where many claims succeed or fail. Those who manage FIDIC contracts as professionals find that having some practical understanding is useful.
Implementing the correct FIDIC contracts includes contract interpretation, claims preparation, dispute avoidance, and risk management. These considerations also differs depending on the used contract form, particularly when comparing between NEC and FIDIC approach for construction projects. Understanding the distinction between NEC and FIDIC can guide you choosing the suitable framework in practice.
Frequently Asked Questions
|
Why are most FIDIC claims denied? Most FIDIC claims are denied owing to lack of notice or untimely notice, lack of sufficient evidence, or the inability to establish the link between the alleged event and its real-time and cost consequences, and not due to the absence of the alleged event itself. |
|
What is the notice period for a FIDIC claim? According to Sub-Clause 20.1 (1999) or 20.2 (2017), a Notice of Claim must be provided within 28 days after the claiming party becomes aware of the event, and it has been confirmed in the courts as a precondition to the entitlement to the claim. |
|
What evidence is required to substantiate a FIDIC claim? Four types of evidence are usually used for a good FIDIC claim: contract documentation, project documentation, programme documentation, and cost documentation, as a claim based solely on one type of evidence is easier to refute. |
|
Why does an extension of time claim under FIDIC frequently fail? An extension of time claim normally fails when evidence is absent regarding the programme, failure of delay analysis, inability to prove the critical path, or neglecting concurrent delays, all of which link the occurrence and the period sought more weakly. |
|
Is it possible for a legitimate claim to be rejected under FIDIC? Yes, a legitimate claim will still be rejected under FIDIC if it fails to meet the notice procedures of the contract. |