Construction Cash Flow Forecast: What You Need to Know

Construction Cash Flow Forecast: What You Need to Know

Last Updated on 1 week ago by Luna

Construction Cash Flow Forecast: What You Need to Know

The cash flow forecast is prepared using the timing of the expenditure and income throughout the duration of the construction. By doing so, you take into consideration the programme, the contract, and your payment conditions, and follow the cumulative gap. You thus know what amount of finance you require and when. The important element here is the timing rather than the value, which is the key difference between a cash flow forecast and a cost forecast.

A project can be profitable but still lack sufficient cash flow, since the costs are paid out prior to the receipt of the money for the particular part of the project. This guide deals with the differences between cash flow and cost, budget, and profit; how the construction payment cycles generate the gap; and the preparation of a cash flow forecast with an illustrative example. Payment legislation is discussed as well.

What is a Construction Cash Flow Forecast?

A construction cash flow forecast is a prediction of the future cash flow on a construction project. The construction cash flow forecast takes into consideration the programme details, costs, payment arrangements, and other commercial data about the project to make the cash flow forecast for the future.

It is important to differentiate between the four terms: cash flow, cost, budget, and profit. The construction project could generate good profit expectations but still have a period of time when the amount of cash to pay out is higher than the amount of cash coming in.

Term What it tells you
Budget The planned financial allowance for expected income and project expenditure.
Cost Amounts the project has paid out or is expected to pay out
Profit The expected financial gain after expenses
Cash flow When money flows into and out of the project
Cash flow forecast Future cash flows will occur

The purpose of the forecast does not determine whether the project is profitable. It is made to demonstrate when cash may become tight, why it possibly happens, and what commercial information needs more attention.

Information Needed for Cash Flow Forecast

Forecasting must be based on accurate data regarding the specific project and not an average construction pay schedule. The first step is to include the worth of the project, its programme, the amount of expected costs, and how the further detail added for labour, procurement, subcontractors, and other commitments will be paid. We list the information and why they are needed for a cash flow forecast in construction projects:

Information Why it is needed
Project value Sets out the total financial magnitude
Project programme Reveals when work and spending are anticipated
Cost forecast Makes forecasts of project expenditures in the future
Client payment arrangements Reveals anticipated cash inflows
Subcontractor commitments Indicates expected downstream payments
Material procurement Reveals major purchasing obligations
Labour costs Reveals labour force expenditures
Plant and equipment Takes into account lease or purchase expenditures
Preliminaries Reveals regular project expenditures
Variations and changes Reflects revisions in anticipated revenues or expenses
Opening cash position Formulates the basis of the forecast

Cash Flow Cycle Throughout Construction Stages

Cash does not necessarily move in line with physical construction progress. There might be high expenditure in the process of acquisition and mobilisation, but there are no corresponding money flows from the client. The money flow pattern will depend on the project being implemented, the procurement approach, and the contractual arrangement; hence the cycle throughout the project delivery shown in the picture below:

Note: This is only a CCM illustration, based on typical relationship between project expenditure, valuation, and payment timing. 

How to Forecast Construction Cash Flow

After gathering the required data, the next step is forecasting, which means putting projected cash flows on a schedule. This task requires linking business data with the project schedule in order for the forecast to reflect the timing of spending and receipts.

Each step below includes why it matters, so the forecast can be checked and not just completed.

Step 1: Time Phasing the Costs Against the Programme

Time-phase the cost plan against the programme by months (or weeks), to reflect expenditure as work occurs. If the cost plan has no time phasing, it does not represent cash, and a programme shift shifts expenditure.

Step 2: Predict the Valuation of Work Executed in Each Period

Calculate the valuation in each period based on the same programme. Payment dates relate to the valuation of work executed, not to expenditure incurred, and will therefore differ because of cost pre-payment or material purchase.

Step 3: Apply the Payment Schedule According to the Contract

Using the due date and final payment date according to the contract, calculate the valuation in the month when payment is received. The difference in dates constitutes the bulk of the funding requirement.

Step 4: Deduct Retention and Other Deductions per the Agreement

Show the retention amount on a different line and use its release date based on the agreement. This will ensure that the retained amount is not treated as cash.

Step 5: Schedule Payment Times

Schedule labour, materials, subcontractors, and preliminaries according to the actual contractual and procurement settings. You cannot make payments ahead of time because your money will fund the difference.

Step 6: Work Out the Net & Cumulative Cash Flow

Net cash flow is the difference between outflows and inflows for each period, while the cumulative net cash flow shows the maximum funding need.

Step 7: Forecast Reviews & Updates

Reforecasting on variations, programme changes, or valuation disputes, and comparing the forecast against actuals for each period. If the forecast is not updated, it becomes inaccurate relative to the actual contract and site.

UK Construction Payment Framework and Cash Flow

For construction contracts within the scope of the Housing Grants, Construction and Regeneration Act 1996, the payment mechanism is directly relevant to cash flow forecasting. The contract should establish and provide a final date for payment. It also must align with the applicable payment notice requirements.

Where the contract does not provide an appropriate payment mechanism, relevant provisions of the Scheme for Construction Contracts might apply. Therefore, the forecast should reflect the actual contractual payment mechanism, including the due date, final date for payment, and applicable notices.

Construction Cash Flow Forecast Example

The example below shows how a project forecast can reveal a cash requirement even when client receipts are increasing. The figures are only illustrative and do not represent a standardised pattern of construction payment.

Cash flow (£) Month 1 Month 2 Month 3 Month 4 Total
Cash In Flow £0 £80,000 £120,000 £160,000 £360,000
Cash Out Flow
Labour £30,000 £45,000 £55,000 £60,000 £190,000
Materials £25,000 £50,000 £65,000 £50,000 £190,000
Subcontractors £10,000 £30,000 £50,000 £65,000 £155,000
Plant and other costs £10,000 £15,000 £20,000 £20,000 £65,000
Total outflows £75,000 £140,000 £190,000 £195,000 £600,000
Net cash flow (£75,000) (£60,000) (£70,000) (£35,000) (£240,000)
Opening Account Balance £100,000 £25,000 (£35,000) (£105,000) –
Closing Account Balance £25,000 (£35,000) (£105,000) (£140,000) –

Note: This is a CCM illustrative example. Figures are hypothetical and provided for explanatory purposes only.

However, the four-month period is just a segment of the cash flow cycle of the project. The total outflow during the four months is £600,000, while inflow amounts to £360,000; hence, there is a net cumulative gap of funding amounting to £240,000, assuming that no opening cash balance is present. Future client inflows can be considered beyond the above-discussed four-month period.

Factors That Change Construction Cash Flow Forecast

A cash flow forecast must always be seen as a flexible business tool that may vary depending on any changes made to the programme, timing of payments, procurement, or the scope of the project. Hence, there may arise occasions when the forecast must be revised.

The table below shows factors together with their impact on the cash flow forecast in construction projects:

Factor Impact on the cash flow forecast
Programme changes Delays and accelerations can affect labour, machinery, material, and subcontracting costs, thereby affecting expenditure and cash receipt timings.
Payment timing Valuations and payment date changes can affect client cash receipts and result in cash flow problems.
Procurement decisions Bringing procurement earlier will increase cash requirements early, and delaying procurement can bring expenditure into later periods.
Variations and scope changes Project changes may result in changes in expected income and expenses, necessitating the update of the appropriate forecast periods.
Subcontractor and supplier commitments Change the timing of the required cash outflows from the project.
Delayed or uncertain receipts Late or uncertain payment may reduce the expected cash inflows and result in a mismatch between the project’s expenses and available cash.

How to Review a Construction Cash Flow Forecast

Assess the cash flow projections in a construction project by looking at how the projections have been performed in relation to the actual movement of cash and if the underlying assumptions for future cash flows still hold good. Focus on changes to the programme, costs, payments by the client, procurement, commitments, and variations.

A practical review should focus on certain areas that lead to questions about what to review in those areas, as shown in the table below:

Review area Question to ask
Receipts Will the predicted cash inflows from clients still materialise?
Expenditure Has there been any change in the value or timing of future expenses?
Programme Is there any shift in the construction schedule?
Procurement Have there been any early purchases or deferred purchases?
Variations Are all relevant changes reflected?
Commitments Are subcontractor commitments valid?
Cash position What is the minimum predicted cash balance?
Assumptions Which are the most uncertain assumptions?

Why is a Cash Flow Forecast Important for Construction Project Professionals?

The importance of cash flow forecasting is that it not only provides an indication of the financial standing of the construction projects but also indicates when the cash will be received and paid out. This means that project workers can be aware of any possible cash problems that future financial challenges could create.

It also creates a connection between business information and project decision-making. It is important to keep track of changes in programmes, procurement processes, valuations, subcontracting arrangements, and payment timings, as these may impact future cash position.

  • Financial Visibility: Shows when you might be spending more money than you’re bringing in and helps you see when you might run short on cash.
  • Commercial Control: Links up project actions with financial actions in such a way that professionals can see how changes in costs, procurement, or programme can influence the commercial situation.
  • Payment Control: Brings forward expected customer payments and payment dates so that potentially delayed or uncertain income is better controlled.
  • Procurement Planning: Indicates when substantial procurements of materials, plants or equipment can be expected, so that expenditure is compared against available cash.
  • Decision Making: Provides current financial data that can help to make decisions on procurement, programme change, commitment and other commercial issues.
  • Early Warning: Detects potential cash shortfall before it happens, so that the project team has an opportunity to review the assumptions behind the forecast and take appropriate measures.
  • Monitoring Project Performance: Allows the comparison of projected cash flows with actual cash flows, which helps to detect changes in project performance or assumptions and update the forecast accordingly.

Build Knowledge in Construction Cash Flow Forecasting

Applying the cash flow forecasting process is about much more than just monitoring cash inflows and outflows. There must be an understanding of how costs, procurement, valuations, payments, and project changes impact one another, thereby offering construction practitioners an overall perspective on the commercial context of the forecast.

For those who wish to develop their knowledge in this area further, formal learning may be able to help in providing this type of joined-up approach along with relevant project experience. Study of project costs, procurement, commercial risks, and finance decisions could offer a more formal method of developing this knowledge base.

Frequently Asked Questions

What is a construction cash flow forecast?

A construction cash flow forecast predicts the timing of cash flows into and out of a construction project. This is based on cost estimates, programme details, and payments to provide a forecast of future cash flows for a specific time period.

What is the distinction between a construction budget and a cash flow forecast?

Budgeting is concerned with planning income and expenses, whereas a cash flow forecast is concerned with the timing of money entering and leaving the project. Thus, a project can be within its budget despite having times of cash flow shortages.

Why is timing of payments important for construction cash flow?

The timing of payment is what dictates when the expected income from a construction project can be used as cash flow. As expenditure can take place prior to receipt, even a viable project will have times of cash flow shortage.

How often should a construction cash flow forecast be re-evaluated?

It is dependent on the scale, complexity, and dynamics of the project in question. In addition, the forecast has to be revised if there are major modifications to the programme, costs, procurement, timing of payments, and scope of the project.

What might influence the construction cash flow forecast?

The projected cash flows may be affected by programme changes, payment delays, procurement problems, variations or changes in the commitments of subcontractors, and unforeseen expenses.